The Norwegian Embassy has had its headquarters on the grounds of the Nordic Embassies extensively renovated. This involved optimizing and converting the lighting as well as the heating, ventilation and fire protection systems. The focus was on saving energy and reducing sound and noise emissions. The refurbishment was carried out floor by floor during ongoing operations.
What services have we provided?
- Project management
- Tendering and awarding of construction services
- Development and management of the relocation chain
The greatest challenges within the project were the increased safety requirements and the conversion during ongoing operations.
Facts and Figures
Duration: 04/2016–03/2017
Client: Royal Norwegian Embassy (Statsbygg)
Location: Berlin, Deutschland
BGF: 225 m²
Investment 400T Euro net (total)
Services: Project management construction and relocation